Our work on the landmark project demonstrated our comprehensive civil construction expertise. As the contractor responsible for bulk earthworks, carpark construction and landscaping, the project showcased our ability to handle complex, multi-stage developments.
Land remediation
Protranz managed the removal of 18,200m³ of asbestos-contaminated material and 1,250m of ACM water main and stormwater pipes. This delicate operation required careful coordination with environmental authorities and stringent safety protocols.
Regular coordination with Otakaro, ECAN, and the CCC ensured all environmental and regulatory requirements were not just met, but exceeded.
Major earthworks and technical expertise
The scope then expanded to include major bulk earthworks, with the team executing a cut-to-waste operation of approximately 50,000m³ and importing 40,000m³ of hardfill material. Technical challenges included the installation of 500m of sheet piling, dewatering of a 4.5m deep pool area, and the precise placement of 70 screw piles.